What's been happening?

Vegetation within the project site area was cleared and mulched in preparation for the earthworks where 85,000 cubic metres of material was excavated and used to create a large sand dune around the east and north of the site.

The dune will help to minimise visual impacts once the area is revegetated at the end of the project. We’ve already started engaging with community groups and other stakeholders to consider how it might look in future and prepare a concept plan.

We’re aiming to ensure the revegetation design is a balanced outcome that reflects the needs of the environment, user groups and the wider community. The final plans will need to be signed off by the Department of Energy, Environment and Climate Action.

Inside the site, a new concrete inlet structure is being built which will see a significant improvement in the treatment process compared to the existing facility. A temporary retaining wall has also been installed to allow for the construction of a new building that will house electrical equipment and aeration blowers servicing the new facilities.

What's the next stage?

Another major phase of the project is due to start in mid September with the construction of two new sewage treatment tanks.

Located beside the four existing tanks, they will enhance the plant’s treatment processes and increase storage capacity by around 50 per cent.

Nearly 200 pre-cast concrete panels will be delivered to the site where they will be lifted in by crane and then joined together with concrete stitch pours to complete each tank.

This is a novel technique and only the third time in Australia that this type of construction has been adopted. It will create time and cost savings for the project.

Project Benefits

  • The plant currently services nearly 15,000 houses - a figure expected to increase by more than 80% to 25,000 properties in the next 50 years.

  • It will allow for an additional $199 million of economic value per annum and 1,512 more jobs for the region by 2040

  • The region’s importance as a food industry hub means that demands on the plant are much higher than would normally be expected

  • We will maintain sustainable sewage and trade waste treatment practices and ensure the environment continues to be protected.

  • We're also developing a new Effluent Management Strategy in accordance with the development licence approved by the Environment Protection Authority.

  • There will be a significant local spin-offs with the construction through the use of sub-contactors, accommodation and food providers.